County Highway 19 (Keats Ave) Corridor Study
About the Study
Washington County, in partnership with the Cities of Cottage Grove and Woodbury, is leading a corridor study for an approximately 5-mile segment of County State Aid Highway (CSAH) 19 (Keats Ave) between US 10/TH 61 and Dale Road. The purpose of this study is to better understand existing conditions, anticipate future corridor needs driven by development, and identify long-term improvement options.
Study Goals
- Develop a deeper understanding of corridor needs and opportunities through a thorough data collection effort.
- Build on technical understanding by gathering stakeholder and public input on corridor condition and needs.
- Develop and build support for improvement options and an implementation approach that outlines actionable strategies to support a safe, connected environment for all users.
Subscribe to Project Updates
Sign up for email alerts to be the first to know about project updates and other ways to be involved in the project by clicking on the button below.
Your input is important to Washington County. Community members are encouraged to share feedback by participating in engagement opportunities or by contacting the County’s Project Manager, Andrea Rehm.
As engagement opportunities are scheduled, they will be posted on this webpage
Pop-Up Events
Cottage Grove Food Truck Festival (September 13, 2025)
Trail side (September 6, 2025)
Welcome to Woodbury (October 23, 2025)
Materials from the Pop-Up Events:
Subscribe to Project Updates
Sign up below for email alerts to be the first to know about project updates and other ways to be involved in the project by clicking on the button below.
The County Highway 19 Corridor Study will involve an approximately 12-month planning process, including data collection and stakeholder engagement opportunities throughout. The project began in Summer 2025 and is expected to conclude in Spring/Summer 2026.
| DATE | ACTIVITY |
|---|---|
| August - October 2025 | Identification of Existing Issues and Needs |
| November 2025 - January 2026 | Identification of Corridor Improvement Options |
| February - May 2026 | Draft Report and Approval of Final Report |
-
Andrea Rehm
Project ManagerPhone: 651-430-4332